I NEED A PERMIT…
How Long Will It take?

Below is a list of “average” time-frames applicants can expect for an application to be approved for permitting.
Assuming all applications are completed in full with all required drawings/seals needed with applicable insurance and bonding forms complete and on file. Applicants should be aware that project changes, weather and other circumstances may effect the time turn around for any and all permit applications.

Most application forms are not yet available on the INTERNET. Applicants may contact the individual department for a faxed copy of a blank form. Applicants could then fax a completed form to the Department for consultation on projected “fees”. Many permits are based on the value of the work to be performed also many permits require “original” attachments before a permit can be issued.

TYPE OF PERMIT
AVG. TIME
DEPARTMENT
(Floor Number and Quadrant)
     
Administrative Special Use 1 week Planning/2 East
Animal License Over the Counter Finance/1 East
Auction 1 week Planning/2 East
Banner Permit 2 to 3 days Planning/2 East
Blasting Permit 3 months Public Works/2 West
Block Party 1 week Planning/2 East
Burn Permit 1 day (24hrs) Fire Dept/Station 3
Cereal Malt Beverage&
Retail Liquor License
1-2 weeks City Clerk/Council 1 East
Day Care Permit 1 day (24hrs) Fire Dept/Station 3
Deck 1 day (24hrs) Codes Admin/2 East
Estate Sale Over the Counter Codes Admin/2 East
Fence Over the Counter Codes Admin/2 East
Re-Roof Over the Counter Codes Admin/2 East
Electrical Over the Counter Codes Admin/2 East
Elevator Over the Counter Codes Admin/2 East
Fire Suppression System 3 days Fire Dept/Station 3
Flatwork 1 day (24 hrs) Codes Admin/2 East
     
Grading
Initial application 2 weeks Public Works/2 West
Final application Over the Counter Codes Admin/2 East
     
Heating/Air Conditioning Over the Counter Codes Admin/2 East
Irrigation Permit
(with new house const.)
1 to 2 days Codes Admin/2 East
Irrigation Permit
(with existing house in ROW)
1 to 2 days Public Works/2 West
New Commercial Construction 2 to 3 weeks Codes Admin/2 East
     
New Development
1st Submittal 3 weeks Public Works/2 West
each subsequent submittal 2 weeks to variable Public Works/2 West
New Residential Construction 1 to 2 days Codes Admin/2 East
Occupational License Over the Counter Finance/1 East
Permanent Sign 1 week Planning/2 East
     
Plumbing
Commercial 1 to 5 days Codes Admin/2 East
Residential 1 to 2 days Codes Admin/2 East
Pool/Hot Tub 1 to 2 days Codes Admin/2 East
Retaining Wall Over the Counter Codes Admin/2 East
Right-Of-Way 1 to 2 days Public Works/2 West
Remodel 1 to 2 days Codes Admin/2 East
Solid Waste
(Trash Haulers)
2 days City Clerk/ 1 East
Sport Court
(with no lighting)
1 to 2 weeks Planning/2 East
Sport Court
(with lighting)
2-3 months Planning/2 East
     
Structure Moving
State Permit Varies along with Traffic Control from Police Dept.
Codes Admin. Approval 1 to 5 days Codes Admin/2 East
Temporary Sign 2 to 3 days Planning/2 East
Tenant Finish 1 to 5 days Codes Admin/2 East
Tent Permit 1 day (24 hrs) Fire Dept/Station 3
 
Print NowPrinter Friendly Version | Disclaimer | Directions | Last Modified: 10/22/2008 2:42:27 PM | Portions of this site require Adobe Reader Portions of this site require Flash Player